Engineers available UK-wide today
Case study · Commercial · Birmingham · 2024–25

3 Chamberlain Square — pre-commission cleaning, disinfection & commissioning.

A landmark 189,000 sq ft commercial development on Birmingham's Paradise estate. BWS delivered full BG29 pre-commission cleaning of the LTHW and CHW systems, chlorination of the domestic water, and water- and air-side commissioning through to client handover.

Exterior of 3 Chamberlain Square, Birmingham — the red and orange terracotta-clad office building on the Paradise estate
189,000sq ft commercial space
10floors plus terraces
4service streams · clean · disinfect · commission · ventilation
30 May 2025Client handover
The project

A landmark Paradise development.

3 Chamberlain Square is one of the standout commercial buildings in Birmingham's £700 million Paradise regeneration. The brief: deliver a Grade A workspace with high-spec end-of-trip facilities, modern washrooms, terraces and changing facilities across ten floors — over 22,500 sq ft of typical floorplate, 24-floor terrace and 200 cycle spaces.

BWS was appointed to deliver the full water-side scope across heating, chilled and domestic systems — getting the building's plant clean, disinfected and commissioned to a programme aligned with the main contractor's handover date.

Scope at a glance

  • Pre-commission cleaning of LTHW & CHW closed systems
  • BG29-compliant flushing, chemical clean and passivation
  • BS8558 chlorination of domestic hot & cold water systems
  • Water commissioning & balancing across all 10 floors
  • Ventilation commissioning to CIBSE Code A across all floors
  • UKAS-accredited sampling and witnessing
  • Fortnightly closed-system sampling post-handover
  • Full evidence pack to client and main contractor
What we did

Three streams, one accountable team.

STREAM 01

BG29 Pre-Commission Cleaning

Full BG29/2021-aligned dynamic flushing of the LTHW and CHW closed systems, followed by alkaline chemical cleaning and inhibitor passivation. UKAS-accredited acceptance sampling against BG29 chemistry targets — turbidity, iron, copper, total bacteria, sulphate-reducing bacteria and inhibitor residual.

STREAM 02

BS8558 Disinfection

Chlorination of the domestic hot and cold water installation to BS8558 — 50 ppm free chlorine, one-hour contact, sodium thiosulphate neutralisation, post-disinfection bacteriological sampling for Legionella, TVC, coliforms and Pseudomonas. BS8558 certificate issued for handover.

STREAM 03

Water Systems Commissioning

Hydraulic balancing of the LTHW and CHW networks across all 10 floors against design flow rates, PICV setting and recording, witnessing of pump performance, and final commissioning data sheets aligned to CIBSE Code W. Full PICV flowrate schedules issued in the evidence pack.

STREAM 04

Ventilation Commissioning — CIBSE Code A

Air-side commissioning of the supply and extract ventilation across all 10 floors to CIBSE Code A. AHU performance verification, ductwork balancing, supply/extract flow rates measured and proportionally regulated, FCU airflows witnessed and recorded against design.

STREAM 05

Post-Handover Sampling

Fortnightly closed-system sampling continued post-handover to verify the chemistry remained within BG50 targets while the building filled with tenants and the system load ramped up. Sample tracker maintained against client thresholds.

Inside the building

A Grade A finish, ready for tenants.

The water-side work supports a finished building delivered to a high standard — from the main reception and end-of-trip facilities to the open-plan floorplates above.

Standards we delivered against

The compliance map for 3 Chamberlain Square.

BSRIA BG29/2021Pre-commission cleaning of pipework
The headline standard for getting a new closed system clean before handover — dynamic flush, chemical clean, passivation, sample evidence.
BS8558Disinfection of potable water
Code of practice for the design, installation, testing and maintenance of services supplying water for domestic use — the standard the BS8558 certificate evidenced.
CIBSE Code WWater distribution commissioning
The technical standard for balancing and commissioning of hydronic water distribution systems.
CIBSE Code AAir distribution commissioning
The technical standard for testing and balancing of supply and extract ventilation systems — used across all 10 floors at 3CS.
BSRIA BG50Closed-system water treatment
The ongoing chemistry standard against which fortnightly post-handover samples were checked.
BS8552Sampling of heating and cooling water
The sampling methodology for the closed-system fortnightly programme.
Outcome

Handed over on programme, clean, chlorinated, balanced.

3 Chamberlain Square handed over to the client on schedule with a complete BWS evidence pack — BG29 acceptance chemistry, BS8558 chlorination certificate, BS8552 closed-system sample tracker, commissioning data sheets, PICV flowrate schedules and photographic evidence — all delivered into the O&M manuals.

The water systems entered service clean, with inhibitor in spec, microbiology at acceptance, and chemistry being monitored fortnightly through tenant occupation. Exactly how a new building's water-side should start its life.

What was delivered

  • BG29 acceptance chemistry — first time
  • BS8558 chlorination certificates
  • UKAS-accredited Legionella, TVC, coliform and Pseudomonas samples
  • CIBSE Code W commissioning data sheets
  • CIBSE Code A ventilation balancing records (all 10 floors)
  • PICV flowrate schedules — LTHW & CHW
  • Closed-system fortnightly sample tracker
  • Full evidence pack into client O&M manuals
Speak to the team

Got a development that needs the same?

Send us your project brief — programme dates, system schematic and handover target. A senior engineer reviews every enquiry personally and comes back with scope, cost and timeline inside 48 hours.